Production

Production Item Details

Edmee

Standard Batch: 1.00 units

Cost per Unit

MVR 5,618.89

Batch Cost (1.00 units)

MVR 5,618.89

Material Cost

$963.89

Labour Cost

$0.00

Machine Cost

$4655.00

Bill of Materials

Material Qty per Unit Unit Cost Cost/Unit
Mirror Acrylic 2mm (Tradefirst)
Area Package: 1.00 sqin
1216.000 sqin per unit
Batch (1.00 units): 1216.00 sqin
1 package(s) needed
$0.2170/sqin
$1000.00/package
$263.89/unit Batch: $1000.00
MMLA Outdoor
Weight Package: 1000.00 g
700.000 g per unit
Batch (1.00 units): 700.00 g
1 package(s) needed
$1.0000/g
$1000.00/package
$700.00/unit Batch: $1000.00
Total Material Cost: $963.89

Labour Operations

No labour operations added yet

Machine Operations

Operation Machine Task Type Time/Unit (min) Rate/Min Cost/Unit
laser cut 3mm Laser Cutter laser cut 3mm 21.00 min $30.00/min $630.00
shell 3D Printer shell 11.50 min $350.00/min $4025.00
Total Machine Cost: $4655.00