Sh. feydhoo hc sign

Standard Batch: 1.00 units

Cost per Unit

MVR 794.34

Batch Cost (1.00 units)

MVR 794.34

Material Cost

$394.44

Labour Cost

$0.00

Machine Cost

$399.90

Bill of Materials

Material Qty per Unit Unit Cost Cost/Unit
PVC Board [12mm]
Area Package: 1.00 sqin
1024.000 sqin per unit
Batch (1.00 units): 1024.00 sqin
1 package(s) needed
$0.1953/sqin
$900.00/package
$200.00/unit Batch: $900.00
Acrylic [clear] 12mm
Area Package: 1.00 sqin
256.000 sqin per unit
Batch (1.00 units): 256.00 sqin
1 package(s) needed
$0.7595/sqin
$3500.00/package
$194.44/unit Batch: $3500.00
Total Material Cost: $394.44

Labour Operations

No labour operations added yet

Machine Operations

Operation Machine Task Type Time/Unit (min) Rate/Min Cost/Unit
Cutting CNC Cutting 30.00 min $13.33/min $399.90
Total Machine Cost: $399.90