Standard Batch: 1.00 units

Cost per Unit

MVR 1,829.34

Batch Cost (1.00 units)

MVR 1,829.34

Material Cost

$1829.34

Labour Cost

$0.00

Machine Cost

$0.00

Bill of Materials

Material Qty per Unit Unit Cost Cost/Unit
Acrylic 6mm
Area Package: 1.00 sqin
2628.000 sqin per unit
Batch (1.00 units): 2628.00 sqin
1 package(s) needed
$0.5046/sqin
$2325.00/package
$1325.98/unit Batch: $2325.00
3mm Acrylic [Clear]
Area Package: 1.00 pcs
1188.000 pcs per unit
Batch (1.00 units): 1188.00 pcs
1 package(s) needed
$0.1975/pcs
$910.00/package
$234.61/unit Batch: $910.00
Mirror Acrylic [Dovira]
Area Package: 1.00 sqin
960.000 sqin per unit
Batch (1.00 units): 960.00 sqin
1 package(s) needed
$0.2799/sqin
$1290.00/package
$268.75/unit Batch: $1290.00
Total Material Cost: $1829.34

Labour Operations

No labour operations added yet

Machine Operations

No machine operations added yet