Production

Production Item Details

Neykurandhoo Quran 2026 Trophy

Standard Batch: 1.00 units

Cost per Unit

MVR 390.84

Batch Cost (1.00 units)

MVR 390.84

Material Cost

$28.34

Labour Cost

$62.50

Machine Cost

$300.00

Bill of Materials

Material Qty per Unit Unit Cost Cost/Unit
Acrylic 3mm (black)
Area Package: 1.00 sqin
26.000 sqin per unit
Batch (1.00 units): 26.00 sqin
1 package(s) needed
$0.2604/sqin
$1200.00/package
$6.77/unit Batch: $1200.00
Acrylic 3mm (black)
Area Package: 1.00 sqin
6.000 sqin per unit
Batch (1.00 units): 6.00 sqin
1 package(s) needed
$0.2604/sqin
$1200.00/package
$1.56/unit Batch: $1200.00
Custom Wooden Trophy Base (M)
Count/Pieces Package: 1.00 pcs
1.000 pcs per unit
Batch (1.00 units): 1.00 pcs
1 package(s) needed
$20.0000/pcs
$20.00/package
$20.00/unit Batch: $20.00
Mirror Acrylic [Red Creatic]
Area Package: 1.00 sqin
7.200 sqin per unit
Batch (1.00 units): 7.20 sqin
1 package(s) needed
$0.0008/sqin
$750.00/package
$0.01/unit Batch: $750.00
Total Material Cost: $28.34

Labour Operations

Operation Labour Type Time/Unit (min) Hourly Rate Cost/Unit
Designer Designer 30.00 min $125.00/hr $62.50
Total Labour Cost: $62.50

Machine Operations

Operation Machine Task Type Time/Unit (min) Rate/Min Cost/Unit
laser cut 3mm Laser Cutter laser cut 3mm 10.00 min $30.00/min $300.00
Total Machine Cost: $300.00