Production

Production Item Details

Tideview Dive

Standard Batch: 1.00 units

Cost per Unit

MVR 1,047.50

Batch Cost (1.00 units)

MVR 1,047.50

Material Cost

$497.50

Labour Cost

$250.00

Machine Cost

$300.00

Bill of Materials

Material Qty per Unit Unit Cost Cost/Unit
3mm Acrylic [Clear]
Area Package: 1.00 pcs
1152.000 pcs per unit
Batch (1.00 units): 1152.00 pcs
1 package(s) needed
$0.1975/pcs
$910.00/package
$227.50/unit Batch: $910.00
Acrylic Spray Paint [Bosny]
Count/Pieces Package: 1.00 pcs
2.000 pcs per unit
Batch (1.00 units): 2.00 pcs
2 package(s) needed
$65.0000/pcs
$65.00/package
$130.00/unit Batch: $130.00
Glue & Tape
Count/Pieces Package: 1.00 pcs
2.000 pcs per unit
Batch (1.00 units): 2.00 pcs
2 package(s) needed
$20.0000/pcs
$20.00/package
$40.00/unit Batch: $40.00
Shipping
Count/Pieces Package: 1.00 pcs
10.000 pcs per unit
Batch (1.00 units): 10.00 pcs
10 package(s) needed
$10.0000/pcs
$10.00/package
$100.00/unit Batch: $100.00
Total Material Cost: $497.50

Labour Operations

Operation Labour Type Time/Unit (min) Hourly Rate Cost/Unit
Designer Designer 120.00 min $125.00/hr $250.00
Total Labour Cost: $250.00

Machine Operations

Operation Machine Task Type Time/Unit (min) Rate/Min Cost/Unit
laser cut 3mm Laser Cutter laser cut 3mm 10.00 min $30.00/min $300.00
Total Machine Cost: $300.00